Valuenator is a somewhat opinionated implementation of feature flow that seeks to automate what’s core and proscribing as little else as practical.

Some important guiding principals:

The core ideas should be automated
The hierarchical relationship between features and tasks is explicit. Task boards are hierarchically displayed within the feature board when features enter a development state.
A team’s activity should be readily visible

It should be possible to see important information on who and what on a computer monitor without scrolling.

The goal of this is to support stand-ups where people don’t talk about what they’re working on, because it’s apparent on the board.

Instead, the stand-up is a chance to address issues, like blocked work or pile-ups in the process, which should also be apparent on the board.

Teams should be self organizing

Tasks aren’t assigned up front by default.

Rather as users pull tasks into working states, like doing or review, they automatically self assign.

Running Valuenator

The easiest way to try Valuenator is with the demo version. This lets you try out the application and get familiar with concepts very quickly without making any commitments or signing up for anything.

You can participate in the on-line beta.

There’s a Docker image that makes deploying Valuenator easy.

Valuenator is an open-source project, which you can modify and run yourself.

Using Valuenator

Using Valuenator amounts to creating and editing features and tasks and moving them through states by dragging cards on boards.

Features start in the backlog, move through several states. When done, features are dragged to “the bag”, where they can be found later, if needed.

Let’s walk through the user interface, as shown in the screen shot below:

_images/sample-board.png

Top bar

At the top of the window is a bar that shows a menu icon on the left. Clicking on this icon opens the navigation drawer, which lets you navigate between boards.

To the right of the menu coon is the title of the current board. On the right of the bar is the avatar of the current user. Clicking on the avatar displays a menu of user options, like logging out or updating profile information.

The avatar comes from Gravatar. Anyone can use Gravatar to associate an avatar image with their email. If a user’s email hasn’t been registered with Gravatar, a random silly image is used. The demo version of Valuenator has sample users with example.com email addresses so their avatars use silly images. If you click on the avatar and select “Profile” from the menu, you can change the email address to use an address registered with Gravatar, and get a real user image.

To the left of the avatar are various buttons. Move your mouse over a button to get a brief description of what it does.

Feature and task boards

Below the top bar is the feature board. Each column in the board represents a feature state [1]. Each feature is shown as a card on the board. You can drag a card with your mouse to move it to a new state.

When a feature is in the development state, its card contains a task board, showing the tasks needed to implement the feature. Tasks are shown as cards on the task board and can be dragged between columns to change their state.

A feature walk through

Let’s see how this works by walking through the feature-flow process.

  1. Create a feature.

    Click on the “+”, add button, below the backlog title.

    A dialog is displayed where you can enter a feature title and description. Enter a title like: “Support multiple browsers”. Enter a description, if you wish and click the “Add” button.

    A card for the feature is added to the backlog. By default, the title is shown and some basic metrics are shown. The metrics, shown as 2 numbers in parentheses, are the total number of completed points and the total number of points in the feature.

    A reveal button to the the right can be clicked to show more information, including the feature description, tasks, and buttons for editing the feature and for adding tasks.

  2. Add tasks

    Click on the reveal button of the feature you just added. You’ll see the description you entered, if any, and buttons for adding tasks (+) and for editing the feature (a pencil).

    Click on the add/+ button. An add-task dialog is displayed. In addition to a title and description, you can specify:

    Size

    The estimated size of the task in points. This is usually just a rough estimate.

    Assigned

    You can use this to assign a task to a member of the team, but it’s usually best to let team members self assign by dragging tasks into working columns.

    Blocked

    This is used to indicate a reason preventing the task from making progress. This isn’t usually set when adding a task. Don’t use this to indicate dependence on other tasks, at least not initially. Blocked tasks get special attention in stand-ups so unblocking them should be actionable.

    Enter a title, like “Safari”. Press enter. This immediately adds the task. The title is cleared so you can add another task. A message is displayed briefly at the bottom of the window indicating that the task was added. This allows a number of tasks to be added quickly.

    Now enter “Firefox [2]” and press enter. This second task is added. The “[2]” in the title indicates that we estimate the task will be roughly twice as hard as the smallest task. When a title ends in a number in square braces, the number is taken as the size. This allows for sizes to be supplied in quick-entry mode.

    Enter “Edge [2]”. Also enter “Need a computer with the Edge browser” in the blocked field. Click “Add and add another”.

    Enter “Write a test script” and press enter.

    Press the escape key to cancel the form and stop entering tasks. Alternatively, you could have clicked the “Add” button to add the previous task.

    A common workflow might be to have story times [2], after which someone does a work-break down to identify the tasks. They’re likely to add a batch of initial tasks.

  3. Now that tasks have been defined, we indicate that the feature is ready to be worked on by dragging it to the “Ready” column on the feature board. The “Ready” column is orderable, so if there are multiple features, we can indicate the priority by dragging to different positions in the column.

    Normally we wouldn’t do this if there was already a feature in the ready column. In fact, we might not bother with taking the time to elaborate features with story times or do work break-downs until the ready column is empty. Requirements and priorities can change very quickly and work can end up being wasted if it’s done too soon.

    In this walk-through though, we’ll take our example feature through the various states even though there are other features in them.

  4. When we’re ready to start working on the feature, we’ll drag it to the development column on the feature board.

    When we do, we see all of the tasks are in the “Ready” task state. Imagine we have 2 developers. Drag the “Write a test script” and “Safari” tasks to the “Doing” column. The tasks are automatically assigned to you and your avatar is shown on the tasks. The task colors switch to green as well to visually emphasize that they’re in a working state.

    Note that when you dragged to “Doing”, the whole column was highlighted. Non-waiting states, like “Doing”, “Review” and “Done” aren’t orderable. Dragging tasks to those states simply adds them to the top of the list of tasks in the state.

    If you’d wanted to make the exercise more more realistic, you could have switched users by clicking the avatar in the action bar, selecting “Switch user” and then selecting a different user to act as. Of course, you could also just reassign one of the tasks. For example, if you click on the expand button for the Safari task and click the edit/pencil button, you can assign the task to someone else.

    In your stand-up meeting you’d note the blocked task because the task is shown with a pink color and shows the blocked reason. You find a suitable computer for testing, and thus unblock the task. Click on the expand button for the task and then the edit button. Delete the text in the blocked field and save. Now the task is shown in yellow, and is ready to be worked on.

    Drag tasks through the phases until all of the tasks are in the Done column. Notice that as tasks are dragged to the “Done” column, the count of completed tasks increases.

    Finally, drag the feature to the “Acceptance” column. It’s shrinks back down to a single card.

  5. Drag the feature to the “Deploying” column and finally to the “Deployed” column. After appreciating your accomplishment, drag to feature to “The Bag”. The feature is now “in the bag”.

You can change your mind and break rules

While you’ll usually drag tasks across boards state by state in one direction, Valuenator doesn’t enforce this. You can skip states. You can drag tasks from one feature to another. You can drag tasks to feature columns, turning them into features. You drag empty features to task columns making them tasks.

Features don’t have to be done to be moved to the Bag. The Bag is a place to put features you don’t want to think about any more. You may for example decide that a feature is too hard and not worth the effort and drag it to the bag. (Bag it.) If you change your mind later, you can pull it back out of the bag.

Empty features

Sometimes features are very small and don’t need to be broken into multiple tasks. If you drag an empty feature into development, a task with an empty title will be created automatically for you. This is useful for tracking progress through development states and seeing assignments. Of course, you can edit this task if you wish.

Working with the Bag

The bag has a reveal button. If you click on it, the bag will expand to show the most recently bagged features. Over time, as you bag more and more value, you’ll have more than can be shown at once. Arrow-buttons at the bottom of the bag let you scroll through features. You can also search for features based on feature and task title and description text.

Each feature is shown with title and metrics and has a reveal button. Clicking on the reveal button for a feature shows its description and tasks. Also shown, at the bottom, is a button to restore the feature from the bag. Clicking on this button restores the feature to the state it was in before it was bagged.

Users

User types

There are currently two types of users: regular and administrative users.

Administrative users can:

  • create and rename boards
  • adjust user types
  • export board data
  • In the future, adjust board states

User-management in the on-line version

The online version currently supports user login using email addresses and passwords [3]. When you set up Valuenator, you need to create a site and bootstrap administrative user.

Once a site and administrative user have been set up, other users can request access. The administrative user can then review and approve access requests and users are send links to set their passwords.

How do I used Valuenator with Jira or github or (substitute your issue tracker)?

We believe that issue trackers should be used to capture problems and opportunities. Tools like Valuenator should be used to create features that address issues. While it might be a good idea to be able to trace from features to issues, we don’t think it’s a good idea to reuse issues as features directly.

We’ll likely integrate with tools like Jira and github in the future. Let is now how important this is to you and what sort of integration you’d like to see by creating or commenting on an issue in the Valuenator issue tracker.

Can I get my data out of Valuenator if I decide not to use it any more?

You’ll be able to export all of your data in a simple JSON format.

[1]States will be editable eventually. This is a planned but so far unimplemented feature. If this is important to you, send an email to feedback@valuenator.com, or comment on the github issue.
[2]It’s common to iterate on stories and multiple meetings are often needed.